Rule-based scheduling of single-stage multiproduct batch plants with parallel units

Bin Shi, Lie Xiang Yan, Wei Wu

研究成果: Article同行評審

11 引文 斯高帕斯(Scopus)

摘要

A new rule-based model for single-stage multiproduct scheduling problem (SMSP) in batch plants with parallel units is proposed. The scheduling problem is decomposed into two subproblems of order assignment and order sequencing. A group of order assignment rules are introduced to select suitable units for customer orders. While flexible constraint handling strategies are proposed to eliminate the constraints of forbidden units and unit release times and convert the hard constraint of forbidden sequences to a soft one, leading to any arbitrary order sequence can be synthesized into a legal schedule. The line-up competition algorithm (LUCA) is presented to obtain optimal order sequence and order assignment rule, which can minimize makespan, total tardiness, or total cost. Through comparative study, the proposed approach has demonstrated its effectiveness for solving a large size SMSP.

原文English
頁(從 - 到)8535-8549
頁數15
期刊Industrial and Engineering Chemistry Research
51
發行號25
DOIs
出版狀態Published - 2012 六月 27

All Science Journal Classification (ASJC) codes

  • Chemistry(all)
  • Chemical Engineering(all)
  • Industrial and Manufacturing Engineering

指紋 深入研究「Rule-based scheduling of single-stage multiproduct batch plants with parallel units」主題。共同形成了獨特的指紋。

引用此